CITY OF NEW BRIGHTON <br />ENGINEERING DEPARTMENT <br />July 27, 2010 <br />CONTRACTOR: GM CONTRACTING, INC. <br />19810515TH AVENUE <br />LAKE CRYSTAL, MN 56055 <br />PHONE: (507)726-6433 <br />FAX: (507)726-6399 <br />CHANGE ORDER 2 <br />PROJECT 09-9, OLD HIGHWAY 8 NW WATERMAIN UPGRADE <br />PURPOSEIDESCRIPTION: 1) During construction the existing 18" forcemain was found to be in conflict with the watermain <br />installation at station 26+70. To properly install the watermain, a portion of the forcemain was removed. 2) The existing <br />watermain service at station 26+75 was found to be inside a 24" casing. The casing was removed and capped with concrete. 3) <br />The existing watermain service at station 33+26 was found to be inside a 24" casing. The casing was removed and capped with <br />concrete. <br />ACTION: <br />THE FOLLOWING ESTIMATED QUANTITIES TO THE CONTRACT DOCUMENTS HAVE BEEN MODIFIED <br />ITEM <br />ESTIMATED UNIT <br />QUANTITY PRICE <br />TOTAL <br />ADD <br />1. Remove Forcemain 26+70 <br />1 HR $595.00 <br />$595.00 <br />2. Cut 24" Casing 26+75 <br />1 HR $595.00 <br />$595.00 <br />3. Cap Casing with Concrete 26+75 <br />1 LS $98.00 <br />$98.00 <br />4. Cut 24" Casing 33+26 <br />1 HR $595.00 <br />$595.00 <br />5. Cap Casing with Concrete 33+26 <br />1 LS $98.00 <br />$98.00 <br />TOTAL OF ADDED ITEMS <br />$1,981.00 <br />TOTAL OF CHANGE ORDER 1 <br />$1,981.00 <br />ORIGINAL CONTRACT AMOUNT <br />$256,940.12 <br />PREVIOUS CHANGE ORDERS <br />$9,848.38 <br />CONTRACT PRICE PRIOR TO CHANGE ORDER <br />$266,788.50 <br />NET INCREASE OF CHANGE ORDER <br />$1,981.00 <br />NEW CONTRACT PRICE WITH CHANGE ORDERS <br />$268,769.50 <br />CHANGE IN CONTRACT TIME <br />NO CHANGE <br />APPROVED BY: f <br />GRANI WYFIf ELS, PE <br />DIRECTOR OF PUBLIC W, <br />CITY OF NEW BRIGHTON <br />APPROVED BY: <br />CONTRACTING, INC. <br />APPROVED BY COUNCIL ACTION: AUGUST 11, 2010 <br />DATE 2 !e <br />DATE <br />