Potential Timeline <br />The perfect time for the RTU and DDC replacement to occur is during the annual NBCC <br />Maintenance Shutdown that occurs the first week in September. Because the facility is <br />closed to the public, there will be no concerns of visitor discomfort or traffic/parking in <br />the parking lots for necessary delivery trucks and cranes to access the building. <br /> <br />March – April Negotiate and execute final agreement with Trane <br />April Verification Process to begin after agreement is finalized, will take 30 days to <br />complete <br />May – July Fabrication of RTU’s would begin after the verification process, three month <br />process <br />August RTU’s delivered to Twin Cities and equipment validated <br />August – September LED Lighting Retrofit <br />September 6-9 RTU and DDC Installation <br />