CITY OF NEW BRIGHTON CONTRACTOR: SUNRAM CONSTRUCTION, INC. <br /> ENGINEERING DEPARTMENT 20010 75TH AVENUE NORTH <br /> CORCORAN, MN 55340 <br /> JUNE 8, 2011 PHONE: (763)420-2140 <br /> FAX: (763)494-3951 <br /> CHANGE ORDER 3 (INCLUDES MNDOT WORK ORDER 5) <br /> PROJECT 08-7, SAFE ROUTES TO SCHOOL, TRAIL CONSTRUCTION AT HANSEN PARK <br /> PURPOSE/DESCRIPTION: This work order is to add metal aprons on the 12"PVC pipe crossings that run beneath the trail as <br /> constructedinch concrete pipe. Additionally,the contractor was directed to haul in additional Class VII to replace soft spots and allow for <br /> paving. This work was not anticipated at the time of the bid and would need to be paid for by change order. <br /> ACTION: <br /> THE FOLLOWING ESTIMATED QUANTITIES TO THE CONTRACT DOCUMENTS HAVE BEEN MODIFIED: <br /> ESTIMATED UNIT <br /> ITEM QUANTITY PRICE TOTAL <br /> ADD <br /> 2211.604 9"Placed Aggregate Base CL. 7(Provided by City) 5 LOAD $250.00 $1,250.00 <br /> 2501.515 12"Metal Flared End Sections 4 EACH $400.00 $1,600.00 <br /> TOTAL OF ADDED ITEMS $2,850.00 <br /> TOTAL OF CHANGE ORDER 3 $2,850.00 <br /> ORIGINAL CONTRACT AMOUNT $313,166.20 <br /> PREVIOUS CHANGE ORDERS $19,557.77 <br /> CONTRACT PRICE PRIOR TO CHANGE ORDER $332,723.97 <br /> NET INCREASE OF CHANGE ORDER $2,850.00 <br /> NEW CONTRACT PRICE WITH CHANGE ORDERS $335,573.97 <br /> CHANGE IN CONTRACT TIME +1 DAY <br /> APPROVED BZei <br /> Y: 1 4,) <br /> DATE (P / <br /> GRANT FELS, E / <br /> DIRECTOR OF PUBLIC WORKS <br /> CITY OF NEW BRIGHTON <br /> APPROVED BY: DATE <br /> SUNRAM CONSTRUCTION, INC. <br /> APPROVED BY COUNCIL ACTION:JUNE 13,2011 <br />