Shank Constructors, Inc. APPLICATION FOR PAYMENT
<br /> 3501 85th Avenue North Project: New Brighton WTP#1 -Chemical Upgrades Application Number: 03
<br /> Brooklyn Park, MN 55443 Shank Project No: 1256 Date: 06/25/13
<br /> Period From: 04/26/13 To: 06/25/13
<br /> A D E F 1 G H I 1 J K L
<br /> Work in Place Stored Material Total
<br /> Item Total Amount Total Amount Total Work& %
<br /> No. Description of Work Scheduled Previous Installed Work Previous Stored Stored Stored Comp.
<br /> Value Payment This App. in Place Payment This App. to Date to Date
<br /> 1 2"Comb.Air Valves on Iron Filters 8,000 8,000 8,000 8,000 100%
<br /> 2 Comb. Air Valves on Misc. Plant Piping 2,800 2,800 2,800 2,800 100%
<br /> 3 Press. Reg.Valve on GAC Backwash 10,000 10,000 10,000 _ 10,000 100%
<br /> 4 14" Backwash Manifold Valve 3,000 3,000 3,000 3,000 100%
<br /> 5 Backwash Pit Float Supports 4,000 4,000 ' 4,000 4,000 100%
<br /> 6 Fluoride Room Modifications 11,000 11,000 11,000 11,000 100%
<br /> 7 Chlorine Equipment Modifications 19,000 19,000 19,000 19,000 100%
<br /> 8 Potassium Permanganate Modific. 16,000 16,000 16,000 16,000 100%
<br /> 9 10" Flow Meters In WH 3,4&15 24,000 20,400 3,600 24,000_ 24,000 100%
<br /> 10 Fridley Booster Pump Station Modif. 40,800 40,800 40,800 40,800 100%
<br /> I-
<br /> Change Orders
<br /> CO#01 $ 1,500 1,500 1,500 _ - 1,500 100%
<br /> Change Order Total $ 1,500
<br /> $ 140,100 $ 135,000 $ 5,100 $ 140,100 $ - $ - $ 1 $ 140,100 100%