Old Highway 8 SW/1st Street NW: <br />Operations <br />I-35W North Corridor Preliminary Design Project 10 <br />Existing Construction: <br />No Mitigation <br />Construction: <br />Mitigated <br />AM 35 95 15 <br />PM 75 3 min +25 <br />Overall Intersection Delay in Seconds <br />Issue: <br />•Volume warrants a signal under existing and <br />construction volumes <br />•SBT volume increases ~200 cars in a.m. peak hour <br />•NBT volume increases ~400 cars in p.m. peak hour <br />•Excessive delay for SB and NB approaches in peak <br />hours <br />Mitigation: <br />•Change Intersection from AWSC to signalized <br />Installation: <br />•MnDOT paying for temporary signal <br />•Consider permanent signal <br />Maintenance: <br />•Ramsey County maintains signal timing during <br />construction <br />1st St NW